Plaintiff failed to prove breach of building contract; conduct varied the contract and defendant awarded K6,800 on counterclaim.
Contract law – building contract – alleged breach for failure to supply fittings – variation by conduct – burden and standard of proof on balance of probabilities – accounting for payments and cheques – counterclaim for unpaid contract balance succeeds.
|