October 2018
Claim dismissed: no proved contract, LPOs were forged and the employee lacked authority to bind the defendant.
  • Contract formation — offer and acceptance — proof of agreement; Public procurement — RFQ/open tender requirements for high‑value contracts; Forgery — forged LPOs are nullities; Agency — actual and ostensible authority; Burden of proof.
24 October 2018
July 2018
The claimant was awarded constitutional damages for prolonged deprivation of liberty due to delayed delivery of appellate judgment.
  • Constitutional damages — Right to trial within a reasonable time — Delay in delivering appellate judgment — Vindicatory remedies under section 46(4) — Assessment of quantum for prolonged unlawful deprivation of liberty.